Storm Water Project Phase 2

Back in 2019 the Foundation carried out the Storm Water Phase 1 project in Triq L-Intornjatur. Following several requests, we managed to come into an agreement with Infrastructure Malta in order to continue the work on the next phase of such project. The plan is that works will start on Monday 3rd October as follows;

Phase 2a – Triq Birrerija (Lower Part) / Triq il- Haddiema / Triq L-Ghajn tan-Nofs

Phase 2b – Triq il-Birrerija (Upper Part)

Phase 2c – Triq L-Intornjatur.

All phases will take approximately 4 to 6 weeks (each phase respectively)

Attached please find the work plans and also the traffic management deviation during the works as approved by Transport Malta. We have also informed the contractor to make sure that businesses & operations are effected in the least possible way during the duration of such works so accesses for garages, offices, warehouses, etc will remain accessible.

If you require further information on this project kindly contact us on info@cbdmalta.org or call on 21446464.